ADU permits and plan check in La Jolla
This is the part of an ADU project owners least want to manage themselves: assembling the package, answering corrections and keeping the clock moving at San Diego's Development Services Department. Here's how the process works under City of San Diego Information Bulletin 400 (January 2026), and what state law adds.

Step by step
- Parcel research. Zone (from the city's Zoning and Parcel Information Portal), Coastal Overlay status and appealable area, Beach Impact Area, fire hazard zone, brush management, historic status.
- Permit type. Building Permit or Combination Building Permit, per Information Bulletin 125. Single dwelling units with ADUs follow Project Submittal Manual Section 2A; other occupancies Section 2.
- Coastal path. Whether a CDP is needed and whether it can be city-issued with the building permit through Process One.
- Submittal. Plans, calculations and forms (DS-3032, DS-16, DS-560) uploaded through the online portal under Building Construction.
- Completeness. Under Gov. Code §66317, the agency has 15 business days to tell you whether the application is complete, with a list of missing items if not.
- Review and corrections. We respond to each cycle of comments and track every reviewer.
- Decision. With an existing dwelling on the lot, a complete application must be approved or denied within 60 days under state law; if denied, the city must return a full set of comments.
- Fees and issuance. Plan check and permit fees, school fees, General Plan Maintenance Fee and any Development Impact Fees. See ADU fees.
- Construction and inspections. Verified contractors build to the approved plans. Changes go through a "Construction Change to a Building Permit" request.
Where La Jolla projects slow down
| Issue | How we handle it |
|---|---|
| Coastal findings | Prepare the CDP material with the first submittal so the coastal review runs alongside building review |
| FAR over the limit | Keep the ADU at 800 sq ft or less, or document remaining floor area |
| Fire separation and openings | Resolve building code distance and opening protection before setting setbacks |
| Beach Impact Area parking | Document the exception (500 sq ft or less, attached, car share, permit district) or show the space |
| Driveway curb compliance | Plan the closure if a conversion makes a curb cut non-compliant |
Preapproved plans
Using a preapproved plan under AB 1332 gives a 30-day review, but the site plan, coastal permit and zone standards still apply. See prefab and preapproved ADUs.
Appeals
If an application is found incomplete or denied, state law requires a written appeal process to the governing body or planning commission, with a final written determination within 60 business days of the appeal.
The San Diego ADU permit walkthrough
- Research: zone and overlays in the city's Zoning and Parcel Information Portal (ZAPP).
- Permit type: IB 400 notes either a Combination Building Permit or a Building Permit depending on units created (see IB 125).
- Submittal set: site plan and vicinity map (IB 122), floor and roof plans, elevations and sections, structural plans and calculations, Title 24 energy calculations.
- Forms: DS-3032 General Application, DS-16 Water Meter Data Card, DS-560 Storm Water Applicability Checklist.
- Apply online: Development Services Application Portal, Building Applications, Building Construction.
- Coastal: in the non-appealable area, a city-issued CDP processed as a building permit through Process One if §126.0708(c) findings are met; not appealable to the Coastal Commission.
- Fees and issuance: per IB 501; school fees per IB 146.
- Changes later: request a Construction Change to a Building Permit.
Plan check correction risks
| Common issue | Prevent it by |
|---|---|
| FAR math unclear | Showing which 800 sq ft exception applies |
| Setback over 16 ft | Dimensioning the 4 ft line |
| Beach Impact Area parking | Stating the exception that applies |
| Sprinklers | Stating whether the house is sprinklered |
| Driveway curb | Showing curb closure if parking is removed |
Who reviews what
| Topic | Reviewer focus |
|---|---|
| Zoning | Size, height, setbacks, FAR, parking |
| Building | Structure, fire separation, egress, energy |
| Fire | Sprinklers where the house has them; Very High Fire Hazard Severity Zone setbacks |
| Engineering | Driveway curbs, storm water (DS-560) |
| Water | Meter data (DS-16) |
Preapproved plans
Using a preapproved plan under AB 1332 gives a 30-day review, per IB 400. You get the plan from its provider; site-specific drawings are still needed.
Sources, checked Oct 14, 2026: City of San Diego Information Bulletin 400 (January 2026) · Gov. Code §66317.
Questions, answered
How do I apply for an ADU permit in La Jolla?
Through the City of San Diego Development Services online portal: under Building Applications, select Building Construction. A building permit is always required.
How long does the city have to approve an ADU?
Under Gov. Code §66317, the agency must decide whether the application is complete within 15 business days and approve or deny a complete application within 60 days when there's an existing home on the lot.
Is a combination permit needed?
Depending on how many units the ADUs create, San Diego issues either a Combination Building Permit or a Building Permit. Information Bulletin 125 explains which.
How do I apply for an ADU permit in San Diego?
Online through the Development Services Application Portal, choosing Building Construction, with the plan set and forms DS-3032, DS-16 and DS-560.