Utilities for La Jolla ADUs
Utility work is the most under-estimated part of many ADU projects. Trenching across a coastal lot, upsizing an electrical panel or routing a sewer line downhill can change a budget more than finishes do. This page covers what San Diego requires in the submittal (City of San Diego Information Bulletin 400 (January 2026)) and what state law says about connections and fees (Gov. Code §66324).

What the city asks for
- Water Meter Data Card (DS-16). Part of the minimum ADU submittal. It documents fixture counts and meter sizing.
- Storm Water Applicability Checklist (DS-560). Determines which storm water requirements apply to the project.
- Title 24 energy calculations and, for new non-manufactured detached ADUs, solar panels (on the ADU or the main house).
Separate connections: what state law allows
| ADU type | Separate connection required? |
|---|---|
| Conversion or JADU within existing space (Gov. Code §66323(a)(1)) | No, unless built with a new single-family home or conveyed separately |
| Other ADUs (new detached, additions) | The local agency or utility may require one, with a connection fee or capacity charge proportionate to the ADU's square feet or drainage fixture units |
State law also says an ADU is not a new residential use for connection fees or capacity charges, unless it's built with a new single-family home. Any fee charged for a required connection can't exceed the reasonable cost of service.
Planning the runs
- Sewer. Gravity matters. A detached ADU downhill from the main sewer lateral may need a pump, which affects cost and maintenance.
- Electrical. Older La Jolla homes often have panels too small to add an all-electric ADU. A service upgrade involves the utility and can set the schedule.
- Water. Fixture counts on the DS-16 drive meter size. If the main house is sprinklered, the ADU needs sprinklers, which affects the water service.
- Storm water. New roof and paving area changes drainage; the DS-560 checklist determines the requirements.
Condos and separate conveyance
If you plan to sell the ADU as a condominium under SDMC §141.0302(f), you must notify utility providers of the condominium creation and separate conveyance, and separate connections become part of the plan. See rentals and condo sales.
Sources, checked Oct 14, 2026: City of San Diego Information Bulletin 400 (January 2026) · Gov. Code §66324.
Questions, answered
Does my ADU need its own water meter in San Diego?
Not always. Under Gov. Code §66324, a conversion ADU under §66323(a)(1) can't be required to have a new or separate utility connection unless built with a new single-family home. Other ADUs may be required to have one, with a proportionate fee.
Are there utility connection fees for ADUs?
An ADU isn't treated as a new residential use for connection fees or capacity charges unless built with a new single-family home. For ADUs that may require a separate connection, the fee must be proportionate to its size or plumbing fixtures.
What utility forms does San Diego require?
The minimum submittal includes the Water Meter Data Card (DS-16) and the Storm Water Applicability Checklist (DS-560).