Answering Plan Check Comments on a La Jolla ADU

A La Jolla ADU permit runs through the City of San Diego, and its review has a rhythm of its own: separate reports from separate reviewers, a locked upload window, and one combined answer. Knowing that rhythm saves a lot of back and forth.

Published Nov 25, 2026

The first time a set of corrections lands, it can feel like a verdict. It isn't. Comments are the normal middle of a permit, and almost every ADU gets some. What matters is how you read them and how you send the answers back.

La Jolla isn't its own city, so your ADU goes through the City of San Diego's Development Services Department. That system has a few rules that surprise people, and they shape how a response should be put together.

How a review cycle unfolds at DSD

Once you apply online and pay the plan-check fees, the project moves into review queues by discipline. Depending on the design, that can mean building, structural, energy, planning and zoning, engineering, storm water, fire and others. Each reviewer works through their part of the plans.

When a reviewer finishes, they issue what DSD calls a cycle issues report for their discipline. Here's the part that trips people up. Even if one reviewer finishes early, you can't upload corrected plans or responses until every discipline has completed its cycle. DSD says so plainly on its permit timeline page.

The city's portal also uses status names you'll see in emails. "Updates Required" means the submittal wasn't deemed complete and more documents or fixes are needed. "Recheck Required" means a reviewer found corrections, and the project repeats that loop until every issue is signed off. "Ready for Final Version" means all disciplines have cleared and the city wants a plan set that reflects all the corrections. After that comes "Ready for Issuance."

Use the waiting time

Because the upload window stays closed until the last report arrives, there's often a stretch where you have some comments and not others. That's useful time. Download each Project Issues Report from the attachments on your record as it lands, and start sorting.

We suggest a simple log with one row per comment: the discipline, the sheet it refers to, the comment in the reviewer's words, who on your team owns it, and the fix. Some comments are a one-line note on a sheet. Others ripple across the set, such as a change to a wall that shows up on the floor plan, the structural sheets and the energy forms.

Watch for comments from two reviewers that pull in different directions. A planning note about a window and an energy note about glazing area, for example, may need one answer that satisfies both. Catching that before you redraw saves a whole cycle.

One package, every discipline at once

DSD doesn't take corrections one discipline at a time. When the window opens, the resubmittal has to answer every discipline's comments together. If more than one discipline asks for a written response, those responses go into a single combined file uploaded as the type the city requested. The city's online guide repeats this for the "Applicant Response to Issues" file: if the responses cover more than one discipline, combine them into one PDF.

A response letter that reviewers can use quickly tends to share a few traits:

  • it repeats each comment, numbered the way the reviewer numbered it
  • it says exactly what changed and on which sheet
  • it points to clouded revisions on the drawings, so changes are easy to find
  • where you disagree, it gives the code section or the reason, politely and briefly
  • it doesn't answer a question the reviewer didn't ask

"Revised per comment" with no sheet number makes a reviewer hunt. Hunting leads to another recheck.

When the coastal piece is in play

Much of La Jolla sits in the Coastal Overlay Zone. Under Information Bulletin 400, an ADU there needs a Coastal Development Permit unless it's completely contained in the existing primary structure without new habitable area or a conversion of non-habitable space. Since September 2022, ADUs in the non-appealable part of the overlay can get a City-issued CDP, issued as a building permit through Process One, when specific findings are made.

Practically, that means some comments may come from planning staff checking those findings. Treat them like any other discipline's comments and answer them in the same package. Our coastal development permit page explains the coastal side in more detail.

Reading a comment before you answer it

Comments come in a few flavors, and each wants a different kind of answer. Some ask for missing information, such as a detail, a note or a form. Those are usually quick. Some point to a conflict with a code section and need a design change. Some ask a question, which often means the reviewer couldn't tell what the drawings intended.

For that last group, the fix is usually clarity rather than redesign. A larger-scale detail, a section cut through the tricky spot or a short note on the sheet can settle it. Resist the urge to change the design just to make a question go away, because a change can open new comments from other disciplines.

It also helps to separate comments that belong to your designer from those that belong to you as the owner. Forms, signatures, utility letters and fee items usually land on the owner's side. Getting those ready while the drawings are being revised keeps the package from waiting on one missing signature.

What state law adds

California's ADU law puts limits on how a city handles an application. Government Code Section 66317 says the agency must tell you in writing within 15 business days whether the application is complete, list what's missing, and not demand items that weren't on that list. Once the application is complete and there's an existing home on the lot, the agency has 60 days to approve or deny. If it denies, it has to return a full set of comments listing the deficient items and how to fix them.

That last rule is your friend. Comments should tell you what to change. If one doesn't, it's fair to ask the reviewer what would satisfy it before you redraw.

After the permit issues

Comments don't always end at issuance. If the design changes during construction, IB-400 points to a separate request in the portal called a "Construction Change to a Building Permit." Field changes made without one can turn into inspection problems later, so it's worth routing them properly.

Habits that shorten the loop

  • Submit what the city's minimum list asks for the first time, including the water meter data card and storm water checklist.
  • Keep one person in charge of the response log so nothing slips.
  • Check DSD's weekly timeline page for current averages instead of relying on what a neighbor heard last year.
  • Ask questions about a comment before resubmitting, not after.

We can't promise how many cycles a project will take or what a reviewer will decide. We work with verified contractors and designers who are used to DSD's format, and we help owners keep the paperwork moving. For the bigger picture, see our plan check guide, or request a Free Quote and tell us where your permit stands.

Sources (accessed Nov 25, 2026): Permit Processing Timeline (City of San Diego Development Services Department) · DSD Online Permitting (Accela) Customer Guide (City of San Diego Development Services Department) · User Guide for Projects with PTS Numbers (City of San Diego Development Services Department) · California Government Code Section 66317 (California Legislative Information) · Information Bulletin 400: Accessory Dwelling Units and Junior Accessory Dwelling Units (City of San Diego Development Services)