The Inspection Sequence for a La Jolla ADU Build

Every stage of a La Jolla ADU gets looked at before it disappears behind concrete, drywall or stucco. The City of San Diego publishes its own list of inspections in the order they usually happen, and walking through it is the best way to plan a build that doesn't stall.

Published Nov 25, 2026

A permit is permission to start, not a finish line. After it issues, the city keeps checking the work in stages, and nothing counts as approved until an inspector has seen it and signed off. The City of San Diego says it simply: all construction must be inspected and approved before it's covered or concealed, occupied or put into use.

For a La Jolla ADU, those checks follow the city's published "Types of Inspections" list. The city notes the list isn't every possible inspection, but it's sorted in the order work usually progresses. Here's how it maps onto a typical backyard unit.

Before any digging: the pre-construction meeting

Some projects need a meeting with city staff before work begins. The city lists the reasons it may be required, and several of them fit La Jolla closely: coastal exemptions, building height, historical resources, number of bedrooms, floor area and high-priority storm water projects. If your permit calls for one, it has to happen before work starts, and the contractor or owner is responsible for scheduling it.

Read your approved plans and inspection record early to see whether a meeting is listed. A height limit or a historic-resource condition is much easier to talk through before a footing is poured.

Below ground

Underground. After trenches are dug and the underground electrical, plumbing, mechanical, fire service and storm water pieces are in, the inspector checks them. Systems that need testing have to be under test when the inspector arrives. On a detached ADU, this is often the sewer lateral, water line and electrical conduit running back to the main house.

Foundation. Footings are excavated, forms are up, reinforcing steel is placed and hardware is tied in before concrete. Anchor bolts and hold-downs that will tie the walls to the foundation are part of what gets checked.

Walls that hold back soil

Hillside lots are common in La Jolla, and an ADU tucked into a slope may come with a retaining or basement wall. Two inspections apply here.

Masonry pre-grout happens as block walls go up, before the cells are grouted. The city limits each lift to 5 feet without cleanouts and 8 feet with them, with all reinforcement in place.

Wall drainage piping is the one people forget. It takes place at least seven days after the wall is grouted or poured, but before backfill goes in. Miss it and the inspector can't see the drain that keeps water from building up behind the wall.

The frame goes up

First floor system. On a raised floor, the inspector looks at floor framing and any rough plumbing, electrical or mechanical work running below or through it. Insulation and floor sheathing wait until this passes.

Exterior wall framing. This comes after the walls are framed, doors and windows are set, and every exterior penetration and opening is flashed. Flashing matters on a coastal site, where wind-driven rain finds weak spots.

Roof system. Roof framing and sheathing get checked, and where a roof has several layers, each one is approved before the next goes on.

All frame and rough. This is the big one. All rough framing is done, and the electrical, plumbing, mechanical and any fire sprinkler work is in place inside the walls. If any electrical work isn't shown on the approved drawings, the city requires a completed and signed Electrical Circuit Card. Insulation can't go in until this passes.

Closing the walls

Insulation is checked after the building is weather-tight and the insulation is secured, before any surface covering goes on. The installer's certificate of compliance has to be provided before the final inspection.

Lath or gypsum board comes next, before stucco, plaster, tile or taping. This stage also includes a shower pan water test, so the shower's waterproofing is proven before tile hides it.

Inspections that run alongside

Some checks don't fit neatly in the line:

  • Special inspections and testing are done by a special inspector or testing lab certified by the city, where the plans call for them. The city stresses these are in addition to its own inspections, not a substitute.
  • Structural observations are made by the architect or engineer of record when the approved plans specify them.
  • Site development and engineering inspections cover grading, drainage and public right-of-way work on the city's schedule.
  • Fire sprinkler final, where a system is required, happens after the piping and heads are installed and braced and the finishes are in.

Keep the site ready for each visit

Most failed inspections we hear about aren't failures of the work. They're failures of access or paperwork. A locked side gate, a dog in the yard, a missing job card or approved plans that aren't on site can all end a visit before it starts. Ask your contractor to keep the permit card and the stamped plan set in a dry, visible spot for the whole job.

It also pays to look ahead one stage. If the next inspection is all frame and rough, the electrician, plumber and mechanical installer all need to be finished first. A single missing strap or an untested drain line can mean a correction notice and a return visit. Walking the work the day before an inspection, with the plans in hand, is the cheapest habit on any build.

When an inspector leaves a correction, read it closely and ask questions on the spot if anything is unclear. Fix it, then request a reinspection the normal way.

Final

The final inspection, which is the approval to occupy, comes only after every other dependent approval is complete. If an ADU is ever going to be sold separately as a condominium, Information Bulletin 400 adds a reason to keep that file clean: the condominium plan can't be recorded until the ADU has final approval of all inspections under its building permit and related permits.

Scheduling basics

  • Standard inspections must be requested at least one day ahead.
  • Online scheduling uses the Inspection Contact number on your permit as a PIN.
  • Inspections run on weekdays from 8:30 a.m. to 3:30 p.m., and heavy demand can push some to another day.
  • Standard inspections are included in permit fees. After-hours or weekend inspections cost extra.
  • The contractor or the owner is responsible for scheduling every required inspection.

How we keep a build moving

A failed inspection usually costs days, not weeks, but those days add up when the next trade is waiting. We work with verified contractors who plan each stage around the city's sequence and keep the job card and approved plans on site. If you're also living on the property, our post on living at home during a La Jolla ADU build covers the day-to-day side. For permit basics, see our permits page, or request a Free Quote to talk through your project.

Sources (accessed Nov 25, 2026): Types of Inspections (City of San Diego Development Services Department) · Inspections (City of San Diego Development Services Department) · Information Bulletin 400: Accessory Dwelling Units and Junior Accessory Dwelling Units (City of San Diego Development Services)