Soils Reports for La Jolla ADUs: Report or Waiver
Some La Jolla ADUs go through plan check with a full geotechnical report. Others go through on a single signed note. The difference comes down to the hazard category of the lot and the ground the unit will sit on.
Published Nov 27, 2026
A soils report, or geotechnical investigation, is a study of the ground by a geotechnical engineer. It tells the designer how much load the soil can carry and what hazards to design around. On a hillside or near the coast, it can shape the whole foundation. On a flat lot with ordinary soil, the City of San Diego may not ask for one at all.
The rules live in two places: San Diego Municipal Code Section 145.1803 and the City's Information Bulletin 141.
Starting from the hazard category
The City's code ties geotechnical requirements to geologic hazard categories from its Seismic Safety Study maps. Table 145.1803 groups them by type:
- Fault zones and ground rupture
- Landslides and potential slope instability
- Liquefaction and potential ground failure
- Coastal bluff stability
- All other terrain
La Jolla has a bit of everything, from coastal bluffs to steep canyons to flatter mesa lots. Your designer will look up the category for your parcel early. The City treats these maps as a guide, not a site-specific answer, so the category is the start of the conversation rather than the end.
When a report is required
Under Section 145.1803, a geotechnical investigation is required for new structures and additions unless an exemption applies, as well as whenever the Building Code or the Building Official calls for one. When a report is prepared, its recommendations have to be built into the plans before the permit is issued.
The code is blunt about two things. The City won't issue a permit where a report shows the construction would be unsafe because of geologic hazards. And issuing a permit is not the City's statement that the site is safe.
The three waiver paths
Section 145.1803 lists situations where the investigation can be waived.
1. Data from nearby sites. If satisfactory data from adjacent areas shows an investigation isn't needed.
2. Smaller additions and alterations. For additions or alterations not in Category 21, where the value is less than 50 percent of the building's replacement value and the added floor area is less than 50 percent of the existing floor area.
3. Lower-risk residential buildings. For Group R-3 buildings, like single-family homes, that are not in Alquist-Priolo Category 11 or Categories 21 or 31, are no more than three stories (or two stories over a basement), and aren't part of a development of four or more homes.
For many detached or attached ADUs on ordinary lots, the third path is the one that applies. Whether your project fits is the Building Official's call.
If no report is required, the plans still have to say so
Information Bulletin 141 explains what happens next. When no report is required, the foundation is designed using presumptive load-bearing values from the California Residential Code. The bulletin lays out the main routes:
- On fill or expansive soil: a preliminary or as-graded geotechnical report is still required.
- Otherwise: the plans can use a presumptive bearing value of 1,500 pounds per square foot, with a signed note acknowledging that the inspector may require a report if fill or expansive soils are suspected during construction.
- Alternative: a design based on Residential Code Section R401.4, with plans signed by a California-civil engineer or architect.
That plan note matters. If the foundation inspector opens the trenches and sees fill or clay that looks expansive, a report can still be required mid-project. A quick look at the soil early can save a stop later.
When the City asks for a recorded notice
On some lots the investigation can't fully rule out a hazard. Section 145.1803 lets the Building Official require a recorded Notice of Geologic and Geotechnical Conditions where faults or other hazards are suspected or the investigation is inconclusive. That notice goes on the property record, so it's worth understanding before you commit to a design.
What a full report covers
When a report is required, the Building Code's Section 1803 sets what it includes: the recommended foundation type and design criteria, plus how to handle expansive soils, liquefaction and expected settlement. On a bluff-top or canyon-edge lot, the geotechnical engineer may also address setbacks from slopes, which can affect where on the lot the unit can go.
How this fits the rest of plan check
The soils decision shows up in several places during review. The structural plans have to reflect it, either through the report's recommendations or the presumptive values and plan note. Plan check comments often ask the designer to confirm the hazard category, show the source of any existing report or add the signed note to the foundation sheet. If grading is part of the project, the earthwork quantities and any engineered fill also connect back to the soils question.
Timing matters too. A geotechnical engineer usually needs a site visit, and on some lots borings or test pits, before writing a report. If you start design before you know whether one is needed, you may end up redrawing the foundation once the recommendations come in. Settling the question at the start keeps the structural drawings and the soils work in step.
Records worth pulling first
Before you hire anyone, look for paperwork you may already have. Many La Jolla homes were built in tracts where the developer had soils or grading reports done. Prior remodels, pools or retaining walls may have their own reports in the City's permit records. A report on a neighboring lot can also be useful, since the code's first waiver path refers to satisfactory data from adjacent areas. Hand whatever you find to the design team; it can shorten the conversation with the City.
Questions to settle before design
- What hazard category is the parcel in?
- Is there an existing soils or grading report for the lot or tract?
- Was the building pad graded with engineered fill?
- Does the ADU qualify for one of the waiver paths?
- If not, how will the report's recommendations fit the layout?
Where we come in
We work with verified contractors and design teams who check hazard categories early, order geotechnical work when the City requires it and build the recommendations into the plans. We aren't geotechnical engineers, and the Building Official, not us, decides whether a waiver applies. Learn more about ADU permits, plan check and detached ADUs, or request a Free Quote.
Sources (accessed Nov 27, 2026): San Diego Municipal Code Chapter 14, Article 5, Division 18 (Section 145.1803) (City of San Diego) · Information Bulletin 141: Geotechnical and Geological Reports for One- and Two-Family Dwellings (City of San Diego Development Services) · 2025 California Building Code Section 1803, Geotechnical Investigations (GoCodebook) · 2025 California Residential Code Section R401, General (Foundations) (GoCodebook)